Answer:
Answer for Part A and Part B is as follows:
Particulars 2016 year 2017 year
Contract Price $13,00,000 $13,00,000
Cost that has been incurred $675000 $950000
Estimated cost to complete $225000 $0
TOTAL COST $900000 $950000
Expected Gross profit $400000 $350000
Percentage that is completed 75 percent 100percent
Gross profit to be recognised $300000 $50000
Note: Calculations have been made according to the data and figures given in the question.