Answer:
c. allocates overhead to activity cost pools, and it then assigns the activity cost pools to products and services by means of cost drivers.
Explanation:
The activity based costing is the costing that helps to allocated the indirect cost or we can say the manufacturing overhead cost with the help of the many cost drivers or the many activity cost pools
Like if we allocate the setup cost so we have to allocated with the number of machine setups.
For the inspection cost, the number of inspections is required so that the allocation could be done