What is a schedule that shows when an item must be ordered from suppliers or when the production of an item must be started to satisfy demand for the finished product by a particular​ date?

Respuesta :

Answer: gross material requirements plan

Explanation: A material requirements plan has been developed for product A based on the product structure of A and the lead-time needed to obtain each component. Planned order releases of a parent item are used to determine gross requirements for its component items.