Answer:
Material Price Variance= $3570 Favorable
Material Quantity Variance= $4620 Unfavorable
Explanation:
Valley View Hospital
Actual number of Plates purchased : 20 ,000
Actual number of Plates used: 17000
Actual price paid per plate : $ 3.99
Standard price per plate : $ 4.20
Material Price Variance= (Actual Price * Actual Quantity)- (Standard Price * Actual Quantity)
Material Price Variance= ($3.99 *17000)-($4.20 *17,000)= $ 67830- $ 71400
Material Price Variance= $3570 Favorable
Material Quantity Variance= (Standard Price * Actual Quantity)-(Standard Price * Standard Quantity)
Material Quantity Variance=($4.20 *17000)-($4.20 *5300* 3)=($4.20 *17000)-($4.20 *15900)
Material Quantity Variance=$ $ 71400-66780= 4620
Material Quantity Variance= $4620 Unfavorable
Total direct materials variance for oil for June= $3570 Favorable - $4620 Unfavorable = $ 1o50 Unfavorable