Respuesta :
Plan A - chase demand by hiring and layoffs will be chosen.
Explanation:
Since this is a chase plan, there is no scope of the stockout and the overtime is also not planned. the following is used to choose the plan.
Qty Demand Production Hire Fire Ending inventory
1500 200
1 1400 1200 0 300 0
2 1200 1200 0 0 0
3 1500 1500 300 0 0
4 1300 1300 0 200 0
Total 5200 300 500 0
Marginal cost $30 $4 $8 $10
Cost $156,000 $1,200 $4,000 $0
$161,200
The question is about the plan that needs to be implemented.
Demand for quarter 1 is 1300 and 200 units is in beginning stock so a production of 1100 units will be required.
In the 2nd quarter a production of 1400 units, 1500 units will be produced in the 3rd quarter and 1300 units will need to be produced in the 4th quarter in order to meet the demand.
The cost will be incurred accordingly and then the plan with the lowest cost will be selected in order to increase profitability.
The lowest cost in incurred in Plan A and therefore Plan A will be chosen and implemented.