Answer: 27 days
Step-by-step explanation:
Hi, to answer this question we have to apply inverse relation:
Since it takes 24 electricians 36 days to wire a new housing subdivision, the relation is:
24 (36)
For 32 electricians:
24(36) = 32 (x)
Solving for x (days)
864 =32x
864/32 =x
x= 27 days
Feel free to ask for more if needed or if you did not understand something.