Answer:
A. Yes Yes
Explanation:
In the case when the cost of completed during the period under the weighted average process costing so both unit cost and the equivalent units to be needed as in the ending period some ending work in process would remains so the transferred cost and the work in process would be transferred to the next period beginning
Therefore the both would be needed