The newer machine works at a unit rate of
(5400 cans) / (180 min) = 30 cans/min
while the older machine operates at
(5400 cans) / (217 min) ≈ 24.88 cans/min
So working together, the two machines work at a rate of about 54.88 cans/min. Producing 5400 cans would then take about
(5400 cans) / (54.88 cans/min) ≈ 98.39 min