When the budget is a constraint, the areas that Ria can adjust to reduce project costs is the project scope and labor utilized
It should be noted that a project simply means the undertaking that's carried out to achieve a goal.
When the time is a constraint, the areas that Ria can adjust to reduce the time in the project is simply by shortening the lag time between tasks and crashing a technique where additional money is spent.
The additional scope can be manged by documenting requirements and creating a change control process.